Amazon Nottingham
Contract Value
£2 million
Client
Buckingham Group
Duration
28 weeks
Project
Scope
EMA3 Amazon Nottingham. PLI Provided all necessary Co-ordination, management, supervision, labour, materials and plant (including tools, equipment and transportation) in order to properly carry out, protect and complete the construction (including temporary works design and construction) of the Groundworks works (The Sub-Contract Works
Drainage included surface and foul water, installation of manholes and inceptor tanks with the use of trench support. Carried out works for the main warehouse, fencing, Road & Car Park, Service Yard, New Exit Road & New Gatehouse, removal of existing concrete structures, sprinkler tanks, piling mat, installation of floor slab. Installation of pumping station and hard landscaping.
Industry accreditations
PL Infrastructure is committed to high industry standards and is accredited by: