SCC Super Computer
Contract Value
£2 Million
Client
Russells WBHO
Duration
26 Weeks
Project
Scope
Supercomputer is a £30 million centre being constructed at Daresbury Laboratories 6.2 acre site. The new centre is part of the Hartree Centre’s £210m National Centre for Digital Innovation (HNCDI), a £172m collaboration with IBM, which provides UK industry access to state-of-the-art digital technologies and expertise.
Once completed, the facility will host the latest in new supercomputing artificial intelligence (AI) and quantum technologies, with the potential for further expansion built in. This will allow the Hartree Centre to grow its capability in the future without the need for additional major construction.
• Earthworks
• Cut and fill
• Foundations
• Roads and associated car parking
• Drainage and ducting
PL Initiated a change in the foundation design. We changed the design to the use of manhole rings this was due to the ground level being too deep causing collapsing and safety issues. We used manhole rings in order to work safely and to achieve cut and fill specification
Industry accreditations
PL Infrastructure is committed to high industry standards and is accredited by: