pl-infrastructure-logo SCC Super Computer

Contract Value

£2 Million

Client

Russells WBHO

Duration

26 Weeks

Project

Scope

Supercomputer is a £30 million centre being constructed at Daresbury Laboratories 6.2 acre site. The new centre is part of the Hartree Centre’s £210m National Centre for Digital Innovation (HNCDI), a £172m collaboration with IBM, which provides UK industry access to state-of-the-art digital technologies and expertise.
Once completed, the facility will host the latest in new supercomputing artificial intelligence (AI) and quantum technologies, with the potential for further expansion built in. This will allow the Hartree Centre to grow its capability in the future without the need for additional major construction.

• Earthworks
• Cut and fill
• Foundations
• Roads and associated car parking
• Drainage and ducting

PL Initiated a change in the foundation design. We changed the design to the use of manhole rings this was due to the ground level being too deep causing collapsing and safety issues. We used manhole rings in order to work safely and to achieve cut and fill specification

Industry accreditations

PL Infrastructure is committed to high industry standards and is accredited by:
pli-logo

Thank you, we'll be in touch soon!

pli-logo

Apply Online

pli-logo

Send Us your Enquiry