M6 J10
Contract Value
£6 million
Client
Sisk
Duration
54 Weeks
Project
Scope
M6 J10. A £6m scheme, consisting of earthworks, drainage, service ducting, connecting to new and existing sewers, chambers, gullies and also, soft and hard landscaping.
Key targets and constraints have been met to facilitate follow on PC Works.
PLI experienced management team worked collaboratively with Sisk to deliver the scheme under challenging conditions, constantly considering VE and dealing with evolving design issues in a collaborative and partnering approach.
Working closely and collaboratively from an early stage and throughout the scheme has instilled trust and belief between our companies.
Industry accreditations
PL Infrastructure is committed to high industry standards and is accredited by: