M6 J13 - J15 ERA's
Contract Value
£2 million
Client
Kier Highways
Duration
12 Weeks
Project
Scope
Construction of 5 new Emergency refuge areas along the new ALR Smart motorway J13-15 M6 .
Very Tight Constraints, single narrow lanes behind zone guard. Works include Earthworks, Drainage, Ducting & Kerbing.
Early works involvement with design, clash identification, product selection. Acceleration of programme to complete the project 2 months ahead of completion. Excellent health and safety record, no incidents, or accidents
Collaborative relationship with the client to deliver the project on time and within budget.
Industry accreditations
PL Infrastructure is committed to high industry standards and is accredited by: